MYRTLE BEACH INTERCHANGE PROJECT OVERCOMES GEOTECHNICAL LIMITATIONS
The design of
a recently completed traffic improvement project in Myrtle Beach, South
Carolina, had to account for significant geotechnical shortcomings to enable
the installation of a 1,250 ft long bridge, the key step in replacing a busy
at-grade intersection with a grade-separated interchange:-
A
recently completed $120-million project entailed a significant reconfiguration
of one of the busiest intersections in Myrtle Beach, South Carolina—the
junction of the U.S. 17 Bypass with S.C. 707 and Farrow Parkway, the latter two
of which converge at U.S. 17. The junction is known locally as the "back
gate" because of its location near what was once the rear entrance to the
former Myrtle Beach Air Force Base. Today the roadways offer access to a mixed-use
development known as Market Commons.
As the "major
north-south artery" for traffic in Myrtle Beach and the surrounding Horry
County, U.S. 17 typically experiences traffic volumes of 70,000 to 80,000
vehicles per day at the intersection, says Mike Barbee, P.E., the regional
production engineer for the South Carolina Department of Transportation (SC
DOT). Another 25,000 to 30,000 vehicles use S.C. 707 and Farrow Parkway each
day. Because Myrtle Beach is a popular vacation destination, the project site
receives significant traffic associated with tourism as well local traffic
seeking to access nearby businesses. Before the completion of the recent
interchange project, the north-south traffic on U.S. 17 "became
increasingly congested," Barbee says, causing long delays at the
intersection. Seeking relief from this bottleneck, Horry County voters approved
a plan in 2006 to dedicate local sales tax funding to pay to convert the busy
at-grade intersection into a grade-separated interchange.
The solution entailed
adding a bridge at the intersection to enable U.S. 17 traffic to pass above
S.C. 707 and Farrow Parkway. In 2008, the SC DOT hired the Rock Hill, South
Carolina, office of STV Group, Inc.—which has its headquarters in New York
City—to lead a team that would provide project management, environmental
documentation, permitting, traffic analysis, roadway and bridge design, utility
coordination, hydraulic analysis, and geotechnical investigations for the
project. The finished bridge consists of a single substructure with two
separate superstructures, one of which carries northbound traffic while the
other carries southbound traffic. This approach was selected because U.S. 17
will have to be expanded from four lanes to six lanes at some point in the
future, and having to widen the substructure again would prove "pretty
costly," says Richard Capps, P.E., a senior vice president of STV. Both
superstructures comprise six spans ranging in length from 140 to 300 ft.
Situated
along the coast of the Atlantic Ocean, Myrtle Beach was built on former
marshland, and the coastal soils provide less than ideal geotechnical
conditions for a bridge project of this magnitude. Because of the flat terrain
at the project site, the planned interchange required the construction of large
ramps and embankments to facilitate the grade separation. At the site, the
soils consist of approximately 35 ft of very soft to firm clay and pockets of
loose sand. After reviewing the results of the borings conducted as part of the
geotechnical investigation, one of the geotechnical engineers involved in the
project described the native soils at the site as "nothing more than
strong water," Capps says.
Faced
with these conditions, the design team had to implement innovative measures to
support the bridge embankments adequately and account for the significant
settlement that the embankments were expected to experience. Ranging in height
from 10 to 42 ft, the embankments were anticipated to settle on the order of 9
to 67 in., Capps says. Deep soil-cement mixing was used to strengthen the
ground in the vicinity of the bridge abutments to enable it to support the
heavy features. To this end, approximately 35,600 cu yd of cement was used to
create adequate foundations for the bridge abutments. Depending on location, cement
mixing depths ranged from 49 to 77.5 ft below the surface.
The
embankments themselves were constructed in conjunction with mechanically
stabilized earth (MSE) walls. Because various project components had to be
constructed at different stages, the MSE walls were also constructed in phases.
"What we had to do was build the ramps for the interchange first, and then
we came back to construct the bridge and the bridge approach embankments,"
Capps explains. For this reason, the design called for the construction of both
temporary and permanent MSE walls, he says. Used to construct the ramp
embankment while traffic remained in its original pattern, the temporary MSE
walls were embedded within the project by the subsequent construction of the
mainline embankment. "For the permanent MSE walls, we allowed settlement
to take place, and then went back and put the final facing on the wall after
the settlement had dissipated," Capps notes. Ultimately, the project
involved the construction of 51,500 sq ft of temporary MSE walls and 30,500 sq
ft of permanent MSE walls.
Because of the critical
nature of the project, the design team implemented measures that would expedite
the settlement process within the embankments so as to accelerate project
completion. For example, thousands of prefabricated vertical drains were
installed in the embankments, Capps says, to facilitate moisture removal and
hasten settlement. All told, approximately 3 million linear ft of prefabricated
vertical drains were used. Another solution involved the use of lightweight
aggregate borrow material as fill for the embankments. Approximately half the
weight of normal material, the lightweight aggregate settles faster and settles
less than typical fill.
Additional improvements
conducted as part of the project included the addition of turn lanes on S.C.
707 and Farrow Parkway and a slight change in the configuration of both
roadways so that they would align better with the new interchange. As for the
aesthetic appearance of the bridge, the design team included bent caps and a
color scheme that would complement the nearby Market Commons development, Capps
says. At the same time, the city logo for Myrtle Beach and the crescent moon
and Palmetto tree that appear on the South Carolina flag adorn various features
of the bridge.
Mead and Hunt designed
the bridge, while GeoStellar Engineering LLC, of Baton Rouge, Louisiana,
conducted the geotechnical design. Civil Engineering Consulting Services, Inc.,
of Columbia, South Carolina, participated in utility surveys and signal and
signing design. Construction was performed by the Wilmington, North Carolina,
office of Balfour Beatty Infrastructure, Inc., which has its headquarters in
Atlanta. The Columbia, South Carolina, office of CDM Smith, Inc.—which is
headquartered in Boston—served as construction manager for the South Carolina
DOT.
Comments
Post a Comment